CAM Variance April 2026
402.04.04.04 CE - Standard Module Assembly Site 2
There is a cumulative schedule variance of -$762k in the cost account 402.04.04.04 CE - Standard Module Assembly Site 2 (CMU). The variance is from the assembly and testing of the first 64% of modules and the associated cleanroom consumables.
This variance is expected, primarily due to delays input parts (baseplates). CMU has now received 100 CuW/200 more Ti baseplates We have been doing a run of 200um CuW modules. This has been mainly done with 8 modules / day protocol. One of our production techincians has be prioritizing setup and commissioning of the thermal unit. We have an offer out to another technician to get us up to 16/day.
There is a cumulative cost variance of -$589k in cost account 402.04.04.04 CE - Standard Module Assembly Site 2. This is expected and is consistent with the cumulative schedule variance discussed below. Schedule delays, due to missing input parts, have caused cost variance resulting from labor costs not earning value.
Impact
The activities contributing to this variance are due to upstream delays in receiving input components needed for the final module test stands, resulting in completion later than scheduled. Once the components become available, the value will be earned, and it should not impact the overall schedule.
402.04.04.05 CE - Module Assembly at UCSB
There is a cumulative schedule variance of -$833k in cost account 402.04.04.05 CE - Module Assembly at UCSB. The variance has two components: most (90%) is due to the assembly, testing, and shipping of full-size equivalent odd-sized modules (1-64%); the remainder is for supporting production at other assembly sites. This past month UCSB has continued to produce modules with 16/day protocol and is catching up earning value given the available input parts.
A major issue that is being worked on with high priority is commissioning the equipment required for high-throughput tests of the assembled modules. This is converging and should be operational soon.
There is a cumulative cost variance of -$1,190k in cost account 402.04.04.05 CE - Module Assembly at UCSB. This is expected and is consistent with the cumulative schedule variance discussed above. Schedule delays, due to missing input parts, have caused cost variance resulting from labor costs not earning value.
Current
There is a current cost variance of -$245k which is the result of labor for module assembly at UCSB (Task: 402.44.501791 CE-UCSB Module Assembly MIE-C UNIV Labor). The actuals reflect a sum of several months.
Impact
The activities contributing to this variance are due to upstream delays in receiving input components needed for the final module test stands, resulting in completion later than scheduled. Input components are now becoming available and value is starting to be earned; it should not impact the overall schedule.