CMU HGC Mac Meeting 30 June 2026

News

  • [ ] Brennan Starts
  • [ ] Baseplates ???
  • [ ] Have loop backs and power adapters
  • [ ] Power Distributers

Action Items

  • [ ] Tray loading pins?
  • [ ] MMTS. Draft best practices
  • [ ] Need 4 power managers

MMTS

  • Sealing the box … didnt help the due point too much -60
  • Due point, was stuck…loose connection?
  • 2nd set of thermal modules…
  • Slides and then proceed…

Jessica

  • No module assembly…
  • Baseplates almost gone…
  • Early to mid july for more baseplates:
  • Magic touch…after 5 min cures

Jim

  • Preparing shipping the baseplates

Ashley

  • Testing hexaboard.

Inna

  • Hexaboard testing

Brennan

  • More testing

Andrew

  • switched to the power adapter
  • Will test with higher volatage 1.6 for the currption

Cooper

  • MMTS code w/Carter …
  • Helping Jasque 18/

Jacques

  • Testing

Arvind

  • Testing

Christian

  • Testing vacuum pump… tubing from cleanroom
  • shipping DB updates

Carter

  1. Almost done with HV cables… All made will be put in
  2. w/Cooper on documentation
  3. Looking into the multipluxer wiring.