MAC Meeting 8 October 2025

https://indico.cern.ch/event/1596840/

Some key takeaways from today's meeting:

Goals for the remainder of 2025

  • 3 month delay in projected milestones
  • more regularly scheduled meetings to focus on technical details as ramp-up progresses
  • possibly separate US and Asia MAC meetings due to time zone differences
  • Communication with other MACs is crucial - if you see a problem, say something because other MACs may run into the same issues

Baseplates Status

  • CuW modules from IHEP being sent to CERN first then to US - IHEP currently working on paperwork for shipping to CERN, ETA still unknown
  • Refer to IHEP CuW notes Slide 11 for examples of "bad" baseplates
  • KIT - QTY 120 Ti BPs possibly ship as early as end of next week, logistics are an obstacle

    End of October is earliest we could receive baseplates

General updates and reminders

  • New pass/fail criteria for wire bonding, please review (especially Jacques and I)
  • I will update the wire bonding programs tomorrow or Friday
  • Don't backside bond, flip, frontside bond, then do all encapsulation like IHEP - flipping without encapsulation is risky
  • Guidance on visual inspections
  • More discussion on Mattermost wire bonding/encapsulation channel to come
  • Some good reminders: use preseries sensors, use correct module labels, throw away old labels, ship modules to CAFs when done

Testing summary, MMTS commissioning, etc

Database Updates

  • Confirmed so far that no differences for V3D and V3E compared to V3C for testing
  • No questions

TTU

  • working on 8 modules per day
  • working with IT for outside network access
  • received some MMTS parts but not assembled yet
  • good offsets for recent modules with 3 having bad IV curves (but maybe not really?)
  • Apparent warping during thermal cycling

CMU

  • No questions, Jacques did a nice job!

IHEP

  • Damaged protomodule due to Z axis not homed during survey - CMU OGP prompts user to home axes when loading software, we haven't had this issue
  • Currently investigating alignment issues
  • Modules testing well
  • OGP getting set up - we sent a link recently to our OGP GitHub that includes training and surveys
  • Setting up MMTS and hiring new personnel
  • 30 minutes or less to wire bond: this includes startup/warmup and actual runtime, which is consistent with CMU

NTU

  • Takes 6-7 hours for 8 modules per day on gantry
  • Electronic test (8 pieces / 70 min) / wire bonding (8 pieces / 3.3 hr) / encapsulation (8 pieces / 4 hr) can be done parallel
  • HV connector casuing noisy channels on partials

TIFR

  • Starting production next week but low on inventory
  • LV working with local DB
  • Also setting up MMTS

UCSB

  • Can assembly 8 modules per day - next step is to start a second round of (proto)modules immediately after first round
  • Also tweaking biasing after each round and seeing improvements in offsets - consistent Y offset in production compared to dry runs for HBs, mostly because of no tape during dry runs
  • Guidance on applying transfer tape on HD HBs - we haven't had this issue for LD, but this was a good FYI
  • Epoxy dispensing rate is fairly constant after 13 mins (or 780 sec) from glue mixing. UCSB advises to mix glue 13 mins before dispensing. It takes them about 12 minutes to find fiducials. We don't have a time on autolocating fiducials yet. We can go back to using one syringe per round if this works. I have a lot of questions and will email Kai after the meeting.
  • Testing LD Full modules from CMU and TTU: need power adapter from Minnesota to finish
  • MMTS setup in progress - Alma 9 for PLC? No answer at the moment
  • Ti BPs have excessive glue in loading pin holes - be aware
  • Will add test data to central DB soon

Closing

  • Discussion about central DB - no conclusion, item for next meeting