HGC Management Meeting
Logs
14 July 2026 Tuesday
Chat about slides:
- Projection in P6… doesnt know there is a delay
- Unresolved technical issue… what will happen
- Assert a t0 … Give my estimates.
- Critcical path wrt 50%
[X]Ping Steve for critcal path… CR- Future
- Production Monitor: https://hgcal-production-vis.docs.cern.ch/overview.html
30 June 2026 Tuesday
- Turn around reports
23 June 2026 Tuesday
- Preparing for the review
HGC Slides for July 2026 Review
[X]CMS Index
- templates
- All progress since last review
- Draft talks in 2 weeks
PWD: uscmsipr26
2nd baseplate issue:
- IHEP CuW: vendor is reporting using a different glue…
What are CTE Mismatches?
CTE = Coefficient of Thermal Expansion — a measure of how much a material expands or contracts per degree of temperature change (typically expressed in ppm/°C or 10⁻⁶/°C).
## The Core Problem
When you bond/sandwich different materials together, each material wants to expand or contract by a different amount when temperature changes. Since they're physically joined, they can't move freely — this creates mechanical stress.
``` Heating up: Material A (high CTE) → wants to expand a LOT Material B (low CTE) → wants to expand a LITTLE
Result: shear/tensile stress at the interface ```
## Why It Matters
The mismatch (ΔCTE) drives stress proportional to:
``` stress ∝ (CTEA − CTEB) × ΔTemperature ```
Consequences of large mismatches:
- Warping / bowing (bimetallic strip effect)
- Delamination (layers peeling apart)
- Cracking of brittle layers
- Fatigue failure under thermal cycling
## Common Examples
Application Materials Concern PCBs / chip packaging Silicon (~3 ppm/°C) on substrate (~17 ppm/°C) Solder joint cracking Coatings Metal + ceramic coating Spalling Optics Glass + metal mounts Stress birefringence, fracture Composites Fiber + matrix Microcracking ## Typical CTE Values (ppm/°C)
- Silicon: ~2.6
- Glass (borosilicate): ~3.3
- Alumina: ~7
- Steel: ~12
- Copper: ~17
- Aluminum: ~23
## Mitigation Strategies
- Choose materials with matched CTEs
- Use intermediate buffer layers (graded CTE)
- Add compliant/flexible interlayers to absorb strain
- Design for stress relief (slots, flexures)
- Limit operating temperature range
26 May 2026 Tuesday
- Getting data from
CMU: 28/127 —> 22% of l157 50-> 75% l170 50-> 75% UCSB: 185 –> 120 + 32 FSE = 152 = 86 (finished 9-16%) 66 (8% start 17-32%) BLRT: 65 Full/5: 120
19 May 2026 Tuesday
- 323 CMU
- 427 TTU
- 600 UCSB ~ 400 FSE
- 1150
12 May 2026 Tuesday
- TTU: 200+ Ti plates are unusable
- Finished CuW today
- QC at the
- Our baseplates also have kapton coming off relatively easily !
28 April 2026 Tuesday
Could it be the Controller… ?… Appears the answer is yes.
- Had 228. 292 =-> Complete 240 … + 52 + 10 (modules from end March)
- CMU + 62 / (4240*0.03) = 62/ 127.2 = 49%
Completed: l 153 ECM-Assemble and test module 81-240 at Site 2 Started l157 ECM-Assemble and test standard modules at Site 2 (5% - 8%) Started l169 ECM- Supervise assembly and testing of modules at Site 2 (5% - 8%)
UCSB: + (33 + 20+ 19+4+3+2+5)*0.5 + 6 = 50
Had: 4908* 0.09 + 4908*0.09* 0.25 = 441.72 + 110.43 = 552 Now … 602
100
l197 ECM-Assemble and test full-size equivalent odd-sized modules (9% - 16%) -> 75% l203 ECM- Supervise assembly of full-size equivalent odd-sized modules (9% - 16%) -> 75%
l156 5% Completion review … Finished
21 April 2026 Tuesday
- FNAL progress review last week in July
- schedule workshop in May 5-6
- Based on what we have in the end of May
- GOAL: is to be just above the depletion
- highest volatages 300 LD
31 March 2026 Tuesday
- Posters for USCMS in Maryland in June
l111 SM21360 ECM: Commission module teststands for production (module sites) 75% -> 80%
l157 SM40170 ECM-Ship module 1 to 80 from Site 2 to Cassette Assembly Site -> 70% l158 SM40180 ECM-Assemble and test module 81-240 at Site 2 -> 95% l159 SM40190 ECM- Supervise assembly and testing of modules 81-240 at Site 2 To 95%
l200 SM60870 ECM-Assemble and test full-size equivalent odd-sized modules (17% - 32%) 25-> 65% l211 SM61070 ECM-Ship odd-sized modules from UCSB to Cassette Assembly Sites (1% - 8%) -> 40%
Modules assembled at CMU during 2026/3 –
| Geometry | Resolution | BP Material | Sensor Thickness | ROC Version | Final Grade | Count |
| Full | LD | Titanium | 300 | HGCROCV3d | A | 54 |
| Full | LD | CuW | 200 | HGCROCV3d | 8 | |
| Full | LD | Titanium | 300 | HGCROCV3d | B | 2 |
| Full | LD | Titanium | 300 | HGCROCV3d | C | 2 |
| Full | LD | Titanium | 300 | HGCROCV3d | F | 1 |
Total: 67 / 4240 = 1.5% 67/160 = 42%
Modules assembled at UCSB during 2026/3 –
| Geometry | Resolution | BP Material | Sensor Thickness | ROC Version | Final Grade | Count |
| Full | HD | CuW | 200 | HGCROCV3d | 100 | |
| Full | HD | Titanium | 200 | HGCROCV3d | 25 | |
| Full | HD | Titanium | 200 | HGCROCV3d | A | 15 |
Total: 140 / 4908 = 2.9 % 140 / 343.56 = 0.41
10 March 2026 Tuesday
- 200um CuT Modues to CERN before end of the month
03 March 2026 Tuesday
Modules assembled at CMU during 2026/2 --
| Geometry | Resolution | BP Material | Sensor Thickness | ROC Version | Final Grade | Count |
|---|---|---|---|---|---|---|
| Full | LD | Titanium | 300 | HGCROCV3d | A | 28 |
| Full | LD | Titanium | 300 | HGCROCV3d | C | 1 |
| Full | LD | Titanium | 300 | HGCROCV3d | 1 |
UCSB: (4908)
Modules assembled at UCSB during 2026/2 --
| Geometry | Resolution | BP Material | Sensor Thickness | ROC Version | Final Grade | Count |
|---|---|---|---|---|---|---|
| Full | HD | Titanium | 200 | HGCROCV3d | 42 | |
| Full | HD | Titanium | 200 | HGCROCV3d | A | 23 |
| Full | HD | Titanium | 200 | HGCROCV3d | C | 3 |
- Moves
- L113 SM21360 ECM: Commission module teststands for production (module sites) –> 50%
- L117 SM23190 ECM: Purchase of shipping cases for UCSB Site -> 100%
- L161 SM40180 ECM-Assemble and test module 81-240 at Site 2 35% -> 53% 35% (56 Modules) -> (86 Modules) 53%
- L162 SM40190 ECM- Supervise assembly and testing of modules 81-240 at Site 2
- L201 SM60860 ECM-Assemble and test full-size equivalent odd-sized modules (9% - 16%) 5%-> 5% (17 modules) -> (85 Modules) 0.254491017964
Last week in July 28-30th
17 February 2026 Tuesday
- 40 loop back
- 24 lv adapters
- Project review end of July
20 January 2026 Tuesday
- Modules
- Absolute number of modules for preproduction plates (l47 ) is small
- Colling plates in April
- 46 and 47 are teh two last layers
- CT shippment has been picked up … so some movement.
13 January 2026 Tuesday
l165 SM40140 ECM-Assemble and test module 1-80 at Site 2
l203 ECM-Assemble and test full-size equivalent odd-sized modules (1% - 8%) l209 ECM- Supervise assembly of full-size equivalent odd-sized modules (1% - 8%)
- Need to order HV wiring
02 December 2025 Tuesday
- UCSB: 46 Modules since 9/26
l200 SM60850 ECM-Assemble and test full-size equivalent odd-sized modules (1% - 8%) Move to 20%\ l205 SM60940 ECM- Supervise assembly of full-size equivalent odd-sized modules (1% - 8%) Move to 20%
Close: ECM: International partner produces base plates Batch 1 Close: ECM: International partner delivers base plates Batch 1 Close l68 ECM: Ship PCB batch 1 to module assembly sites
Do we have a power distribution board? LV: 1.8 V supply
11 November 2025 Tuesday
- The modules flattened after cooling
- Check them for noise
- Keep modules until we have done the thermal cycling on them
04 November 2025 Tuesday
- Turnaround report
- l 121 402W.04.04.02.04 CE - Module Site 3 SM61430 ECM: Procurement of final module factory tooling for UCSB marked done: Moving 194 ECM-Assemble and test full-size equivalent odd-sized modules (1% - 8%) to 15% Moving 199 SM60940 ECM- Supervise assembly of full-size equivalent odd-sized modules (1% - 8%) to 15%
- 100 Ti fulls to TTU and CMU
- Check out valves: flow limiters / flow restriction
- Serial flow
- Thermal P60
16 September 2025 Tuesday
- Chambers have been picked up some time ago… not alot of details about where they are (No number)
- Shelves not yet sent.
- Steps in baseplates and TIB
09 September 2025 Tuesday
- Ship modules to TTU for thermal cycling ? and UCSB…
- TTU got baseplates
- Looks like none sent to CMU
02 September 2025 Tuesday
l159: 44->56%
- Buy the boxes !
- PCBs wait until the reentry
- UCSB will probably build modules in September
05 August 2025 Tuesday
- Working on July CAM Turnaround Report
- Shelves being machined at CERN
- Box and shelves coming seperately
- Closed out: lines associated with chiller and teststand electronics: line 94 and 95, 102, 106, 110
- Also did 100
- UCSB: four more
- Zoltan wants modules
29 July 2025 Tuesday
- CuT incoming ? 1-2 months out
- 8 Krias coming from CERN
15 July 2025 Tuesday
- Need more trophys
- Should empty them and ship back.
- Talk with Dave to see turn around on the hexabord crates.
[X]Follow up with Alabama- In short-term will get trophy only connectors: components on mezzine cards
- Check with Matt about tropy
- No meeting next week
01 July 2025 Tuesday
- Filling out CAM Turnaround Report for June
- l127 End ECM: Delivery of High Voltage Power Supply and Dry Air Supply SM61520
- l135 Advance to 40% SM23190 ECM: Purchase of shipping cases for UCSB Site
- Nothing else unfortunately…
10 June 2025 Tuesday
- Start l127: ECM: Delivery of High Voltage Power Supply and Dry Air Supply to 50%
- CAM Turnaround Report
- Harry assembled 30/60 Krias No fan.
- No SD cards
- Pinged Andrew re:buying fewer boxes
02 June 2025 Monday (No meeting but did turn around)
- Start l127: ECM: Delivery of High Voltage Power Supply and Dry Air Supply to 50%
13 May 2025 Tuesday
- Chatting about presentations
- HGC Slides for June 2025 Review
06 May 2025 Tuesday
- Chatting about the travel
- Risks
[BROKEN LINK: E58C60ED-9000-4234-835E-F6E00D672FCE]
- Turn around report
- CAM Turnaround Report
- Do we start 142 ?
- Complete 152
- Move along: 155 50 -> 75%
- Move along 156: 80->90%
- What is l157 ?
- move along 182: 37->44
- Move along 183 37 -> 44
- Move along 184 20->30 %
- Move along 205 -> 5->7%
15 April 2025 Tuesday
- South Dakota losing their grant unless they comply with 15% overhead
- 2 chiller boxes shipped each week
8 April 2025 Tuesday
- Tariff discussion
- Discussed spare bond head … kick the can down the road
1 April 2025 Tuesday
- Moves:
- l140 SM61440 ECM: Procurement of final module factory tooling for Site 2 (80 -> 90%)
- l143 SM61430 ECM: Procurement of final module factory tooling for UCSB (10->50%)
- l170 SM40140 ECM-Assemble and test module 1-80 at Site 2 (25->37%)
- l171 SM4015 ECM- Supervise assembly and testing of modules 1-80 at Site 2 (25->37%)
- l172 SM40170 ECM-Ship module 1 to 80 from Site 2 to Cassette Assembly Site (start )
- l189 SM50180 T5 - Start of Module Production (UCSB) (start)
- l190 SM50210 ECM: Cleanroom consumables (UCSB)
- CMU Modules per Month
- UCSB Modules per Month
25 March 2025 Tuesday
- https://indico.cern.ch/event/1531110/
- [>>] Need to start filling in the slide template (2 weeks)
- Give the percentage change in labor
- Reference to the docDB area for BoE … Have not produced a BCR b/c the estimate is close … impact … Strong confidence complete with in projected budget.
- L2 is only LoE
- [>>] Update the docs
18 March 2025 Tuesday
- Short and sweet
- Office of project assessment at FNAL
- Estimate to complete important
4 March 2025 Tuesday
- Need expect finish l119-122, 125: module teststand
- Advance L134: 10% -> 40% Start L135: ECM: Purchase of shipping cases for UCSB Site 10% L136: ECM: Procurement of final module factory tooling for Site 2 10% -> 80% Start L139: ECM: Procurement of final module factory tooling for UCSB -> 10% Advance L140 ECM: Oversee the procurement of the final module factory tooling -> 80%
- Module Assembly Site2 Advance L164 ECM-Assemble and test module 1-80 at Site 2 -> 25%
25 February 2025 Tuesday
- l129: SM23180 ECM: Purchase of shipping cases for Site 2 10% -> 50%
- L131 SM61440 ECM: Procurement of final module factory tooling for Site 2 10->50% l157: ECM-Assemble and test module 1-80 at Site 2 L158 ECM- Supervise assembly and testing of modules 1-80 at Site 2
- Steve leading discussion
- Looking at total float
4 February 2025 Tuesday
- Need monthly counts of how many modules we produce
- Clarify plan with Joe / Suzzane
- Progress Review: DOE wants annual progress reviews.
- W-F April 23-25 DR / June 2-6
28 January 2025 Tuesday
- https://docs.google.com/spreadsheets/d/1xKAJivTT7h8V_19VESxchGj72AXIC5QdW3N6lRbtnqQ/edit?gid=1245728450#gid=1245728450
- Module assembly at CMU
- Moves: l81: ECM: Test standard PCB batch 1 (First 5%) to 20% l157: ECM-Assemble and test module 1-80 at Site 2 l158 ECM- Supervise assembly and testing of modules 1-80 at Site 2
- From Barney:
- I strongly suggest you follow the P2UG presentations by HGCAL that happen 1-2 times per year, as this sort of thing is always mentioned. You can look at Paul's presentation at the November P2UG ([https://indico.cern.ch/event/1471927/contributions/6197528/attachments/2959391/5207889/HGCAL%20Electronics%20P2UG%205Nov24.pdf](https://indico.cern.ch/event/1471927/contributions/6197528/attachments/2959391/5207889/HGCAL%20Electronics%20P2UG%205Nov24.pdf)) for a reasonable summary of the status of the Hexaboards.
- Since November:
- about 1500 more LD Full Hexaboards received at CERN (bare). Visual inspection done on a sampling basis - all very good
- 60 LD Full assembled with HGCROC3C before Christmas and tested recently: look good (with the provisos of 3C of course)
- Orders placed with an assembly company (one we know well) for assembly of another ~900 boards - mostly Full, but also some partials - to get the MACs producing modules for the pre-series cassettes and to prove (again on a sampling basis) that the batches of PCBs are ok. These assemblies should all be done with 3C.
- Invitations to Tender for mass assembly will be launched at the end of this week, with mass assembly then due to start around April/May
7 January 2025 Tuesday
- CAM Reporting
- Moved baseplates to 15% (lines: 64 and 65)
- Baseplates: 8 + 34
- Batch 1 = 240 modules/
- Module assembly at CMU
- Start 74 ECM:Vendor delivers assembled standard PCB batch 1 (First 5%)
- HAve 48 hexaboards
- Start 78 ECM: Test standard PCB batch 1 (First 5%)
- Start 81 ECM: Snhip PCB batch 1 to module assembly sites
- Start 106? (Have Kria at CMU!)
- Start 149 150
- close 116 / 123
- Added expected for 149 and 150
- Moved baseplates to 15% (lines: 64 and 65)
- Follow up with Dave
- is the bae PCB proceeding ? (order out for a while)
- assembly still underway
- CAM Turnaround Report
- https://docs.google.com/spreadsheets/d/12NhkWpOrwotOBbPfx21_r1S_-IWLX1YuRGmjqPmBb_0/edit?gid=1225274733#gid=1225274733
- MAC meeting 18 December 2024
17 December 2024 Tuesday
** BCR
- There are overheads ~20% but vary by University (which is why my numbers arent identical)
- https://indico.cern.ch/event/1356090/contributions/5710303/attachments/2768555/4823054/MMStand-ShoppingList.pdf
- from https://indico.cern.ch/event/1356090/
- https://vastitec.com/en/products-2/safety-2/high-voltage-switching-system/
- https://www.tek.com/en/products/keithley/source-measure-units/2400-standard-series-sourcemeter
- Ping Rong Shoang about mimimum requirements
- Ping Joe and Nural about HV 2410
[>>] (HGC Transfer Tape BCR)
3 December 2024 Tuesday
- connected at the end
- discussion of if we can store module is ambient air
26 November 2024 Tuesday
- HGC MAC BoEs
- Turnaround: https://docs.google.com/spreadsheets/d/1wmcJ2myS0LIQdlsP8n9IuCanh3bSH0BrJ9gDTFIXmoU/edit?gid=1373113300#gid=1373113300
- Krias coming to the MACs
- 1 unit
- 5 units/MAC in March
- No schedule for the Trophies https://fbcr.fnal.gov/Account/Login?ReturnUrl=%2FBCR%2FAll https://fbcr.fnal.gov/BCR/All
19 November 2024 Tuesday
- Our meeting today will focus on the risk register, where we need to take
a number of actions, and the planning of a set of BCRs which we need to attack to be able to properly budget for production as well as to defend our plans during the DOE progress review in June.
- Progress Review in Directors Review in April and DOE Project review in June
- ** BCR
| -------------- | ------------------- | ------------------------------------------------------------- | --- | ---------- |
| MAC and Module | J. Alison (w Nural) | Hybrid assembly costs, testing infrastructure remaining costs | December 5 | |
29 October 2024 Tuesday
- Making Moves!
- [>>] Need to ship modules to FNAL
- Turn around report: https://docs.google.com/spreadsheets/d/1_n3haNSgdGix-USM7QhdwhWFtRAPt12EgQ8hgiNsBP4/edit?gid=843171142#gid=843171142
** Making Moves Ending preseries
Finished lines
- l67? ECM: Update base plate design for production modules
- l68 ? T4 - Ready for base plates production
- l69: ECM: Vendor produces preseries partial module base plates
- l73: ECM: Vendor delivers preseries partial module base plates
- l74: ECM: Qualify base plates for production
- l75: ECM: Qualify partial module base plates for production
- 176: ECM: Ship base plates to module assembly sites for preseries production
started:
- l70? ECM: International partner produces base plates Batch 1
Should start ?
- l130 ECM: Procurement of final module factory tooling for Site 2
- l134 ECM: Procurement of final module factory tooling for UCSB
- l128 T5 - ECM - Site 2 Ready for Module Construction
- ** Nural placed order for chillers
- is done!
- 5 POs
- coolant
- Shipping date ?
- Dimensions of the chiller?
- ** Cost on Shipping Foam? $5523.00.
- ** Plan to send to 20 send by end of the month.
- Get shipping address from Don
15 October 2024 Tuesday
- ECON-D has a problem in the SRAM (Static Random-Access Memory)
- ECON-T doesnt have any SRAMs
8 October 2024 Tuesday
Karl wanted a workshop at FNAL
- When cassette was ready, people would come to work on it.
- Karl wanted to have it any way.
- "Site visit" managers DESY and CERN
- Date Nov 11-15th
1 October 2024 Tuesday
- https://docs.google.com/spreadsheets/d/1z-ugaRIo4SszJzNrT5N7ddWe7vlk615xH2ospkZQoS4/edit?gid=983055628#gid=983055628
- Motherboard updates: will produce some LD engines (have PCBs) only enough to get started, while we figure out lpgt situation. (~100)
- HD wagon back, starting to work on
- LD wagon pretty advanced, PCB order soon (limited until Dec. b/c wag side of engine <-> wagon supply delay)
- Modules Baseplates… 22nd 23rd. 29th
- Who to bug about baseplates?
- Propose to finish l163 (odd-size preseries)
- Need to mark completed in tab "Comp Status-DOE"
10 September 2024 Tuesday
- Engine problem, which chips not getting the clock
- Monday Management meeting ?
3 September 2024 Tuesday
Session to exchange news.
- Chiller
- Order placed for shipping material now
- Tooling will be ordered soon
- Xometry designs with interface at FNAL
27 August 2024 Tuesday
- CMU Marked 100% for Preseries
- Mitchell Wayne (Notre Dame) https://physics.nd.edu/people/mitchell-wayne/
- Need to mark completed in tab "Comp Status-DOE"
- https://docs.google.com/spreadsheets/d/1uuUD5JkIhXx8zDhtWwWRrfelDgBqR3iYWHE5NqkY5iU/edit?gid=1977079858#gid=1977079858
13 August 2024 Tuesday
- Tiles and cassettes
- no meeting next week
30 July 2024 Tuesday
- Racheal to send CMU ~125 sensors next week.
- We need 300 micron LD partials early
- The HD partials see the most radiation and will need the best componets to survive.
- ROC v3-b is the chip with probems
- v3-c
- LD require 3 chips / module
- HD require 6 chips / module
- Might be possible for v3-d
- BCR: everything outside freeze to sit on working schedule dates
23 July 2024 Tuesday
Data base and labeling discussion
Local DB working well:
- Need to understand how often to upload to the global DB
- Need to finalize info to be stored
16 July 2024 Tuesday
- Baseplate updates